Question on prod orders

$
0
0

Hello All,

 

I am very new to the concept of prod orders. i would like to understand the following

1. If a prod ord is TECO enabled, it means it is technically completed. Can any postings be done on it after that?

2. If settlement is done on a TECO order, does it generate any doc/posting date etc?

 

Also i have an issue - . For a TECO order which has not been changed since 2007, I have postings for 08.2015. I went to COR3->Cost->Analysis->Set the time frame to 008 2015- I get values calculated. Upon double clicking i do not see any line items, nothing gets generated.

How can i know where these values are coming up from?

 

i have also read on one of the discussions, that on a TECO order month-end activities can be done. Will these generate any posting date as such? The only hint I have is posting date.

 

I am basically an SAP BW resource. Please help me understand the above.

 

Thank you,

Sadaf