REM dep reqs requirement quantity not reduced when reporting pt backflush done

$
0
0

Hi Experts,

 

In REM, I have a planned order that has 2 reporting points. I have reported backflush on reporting point 1 for some quantity. the component quantity is good issued. but the requirement quantity for this component is not reduced in RESB of the planned order.

 

I found a note for this 459960. This note explains the behavior but it says sap doesnt have any solution for this.


my issue is when I run mrp after reporting point backflush, system thinks the component is still needed (because the requirement qty is unchanged) and orders more procurement proposals. in reality I have backflushed the component and I dont need them anymore.


what options do I have as a workaround?