Block GRN for next month -packaging components
Hi Team, Our supplier is sending material for one month advance even though the requested date in PO is next month.we need to block it means, if the requested date in next , system should not allow any...
View ArticleIs there any report to know the planned/ actual Activities & RM consumption
Dear PP experts, Could you please let me know is there any report to find the actual and planned labor, machine, setup hours and also required raw material consumption based on production order. We...
View ArticleExpiry date Production Batch
Dear sir,At present expiry date for a production batch is maintained as Date of manufacturing + Total shelf life. For example if the date of manufacturing is 02/2016, shelf life is 24 month, expiry...
View ArticleAbap runtime error'' RAISE_EXCEPTION'' while conducting COR2
Dear Experts, User is getting Abap dump while is releasing the process order.Appreciate if you can point out the probable error from where it is coming from. ST22 screen shot Best regardsShailesh...
View ArticleGeneral extra material's requirement when MRP
Hi All, I meet a problem in our company. We usually create PIR for our prodcut A, then run mrp general the PR, PR-->PO, PO GR come to stock, finially SO(product A) PGI to consume the stock...
View ArticleWIP Batch
Hi Gurus I have 3 step production operation and at the end of each operation, I create a WIP batch. At the end of the 3rd operation, I am trying to link my WIP (at the top most level) to the GR batch...
View ArticleMCPS - LIS update the last changes on the production order as TECO - Time zero
In our process we analyze the MCPS result to have some information system about result production in a certain periodo entry. In this analyze is knowledge that when the orders are complete confirmed or...
View ArticleBatch Data
Hi, After Batch derivation SLED and DOM is updated on batch. I need to know can we restrict user not to change batch data? I mean SLED and DOM should not be changed after derivation. Thank You, Rupali...
View ArticleConfirmation Issue
Dear SAP Gurus, User is deleting Raw material from the process order while confirming process order. I want User can not be able to delete Raw material while confirming Process order.If any setting...
View ArticlePlant level authorisation in CA81
Hi All, I want plant level authorization for T Code CA81. I have created 1 role & provided C_ROUT & enter 1 plant 1000. During CA81 if user enterd 1100 plant he can execute this report. How can...
View ArticleMass update of Auth.Gr. for BOM
HI ... How to carry out Mass update of BOM header group with an authorization group field ?The purpose of this is to restrict access to design BOM, BOM header authorization group is needed.
View ArticleWrong Calculation of rescheduling date in MD04
Good afternoon. I have noticed the following strange behavior of the system when i run MD04 for some materials. In the first screen, you see that MRP suggests i reschedule in my proposal at 21/06/2016,...
View ArticleAdd BoM Custom Field to batch structure in LSMW
Hi, I found few months ago a very helpful document in SCN about how to add a BoM custom field to the standard batch structure in LSMW. I'm searching with different words both in google and in SCN but I...
View ArticleEnter Valuation type for assy material- MFBF
Hi, My material is Split valuated & batch managed. While doing REM confirmation through t.code MFBF system asks for valuation type for which there is no any dialog box to enter. Kindly guide me to...
View ArticleAssessment stock by material group
Hi gurus! Thanks in advance for help me... I have one requirement that i don't know how i can resolve it. The key user wants show a report of material assessment by group of material and cross-plant....
View ArticleMaterial Master - Mixed MRP Indicator for KMAT
Hello Team, I am creating KMAT configurable material. And I am using the strategy group 11 - gross requirements planning (I have changed the standard setting of requirement class '030' in OVZG with...
View ArticleCancel COFC error but posted HRS on orders
During last month end process order closing our FI team found - they were not able to close few orders because there we errors lying in COFC transaction. Now to clear these errors we have created...
View ArticleBOM data Migration with ECN
Hi Everybody, I'm trying to migrate the BOM's data with the ECN reference, with an LSMW based on a record of transaction CS02. The problem is that when I give in input to CS02 the change number and an...
View Articlereservation issue
Dear Experts For my production order cuobj field is missing against reservation number in resb due to which my characteristics are not displayed in production order . what could be reasons for these...
View ArticlePlanning Strategy - Gross Req Planning - 11
Dear Team, I have created FERT material namely M1 which is material variant of KMAT material namely "C1". For this material variant M1, I have assigned the planning strategy 11 (Gross requirements...