Hi,
I am testing planning strategy 40 and here is the scenario
Avl Stock 200 GAL
PIR: 300 GAL
Sales Order: 600 GAL
When I ran the MRP the system proposed a planned order for 400 GAL and the entire PIR gets consumed by the sales order. I am trying to understand how it came up with the planned order qty and I was expecting a higher qty. The 400 will meet only the sales order req along with the existing stock so how about the PIR requirement?
Thanks
Sachin