Collective Order : multiple orders for same product

$
0
0

Dear all,

 

here is the situation I met in my company :

 

My production ordrers are defined in a collective order model.

 

A consums B

B consums C and D

C consums D

 

When I create an order, here is the result

 

Order for A

      Order for B

               Order for C

                      Order for D

                Order for D

 

In reality, we would like to get only one order in my collective Order model for product D.

Is there a way to ask SAP to  creeate only 1 order by product, Inside a collective order ?

 

Thansk for your help

 

Pierre


Regarding Final confirming a Confirmation in SAP PP

$
0
0

Hi All,

 

There can be different employees(PERNRs) who can work on a confirmation linked to a Production Order/Operation simultaneously.

My requirement is before an employee does a final confirmation to a Confirmation, I need to check whether there are any open time tickets

that are created by other employees( i.e if other employees are still active on that confirmation) and if yes I have to display the list of employees that are still active on that confirmation.

 

Do we have a function module for this? What should be the approach?

 

Regards,

Rahul.

PR generated from MRP run exceeded maximum lot size

$
0
0

Hi gurus,

 

Need some guidance on the scenario below :

 

MRP run for material A

MRP type : VB

Lot size: EX

Maximum Lot Size : 200

 

Material A is a component of material Z. From a previous planned order of material Z, the requirement quantity of material A is 5000.

 

Now, after the MRP run for material A was done, a PR was generated with quantity of 5000.

 

My question is why was the PR generated with the requirement quantity of 5000 and not only did not obey the maximum lot size but exceeded it as well?

 

Thanks.

Planning table for REM - MF50

$
0
0

Hi,

 

In planning table, not able to see the required hours and available hours. Means required capacity and available capacity. can you help.

 

BR,

sam

Lost of the info structure S026

$
0
0

The last week some people created a transport for transaction COR4 and we lost the information of the table s026, we need restructure this information again.

 

 

We lost the information of the last 3 years, only we have the new movements of consumption.

 

 

How we can rebuild this table (S026)?

Hi experts can you please tell me what is the difference means strategy and LSF VSF functions

$
0
0

Hi experts can you please tell me what is the difference means strategy and LSF VSF functions

MRP RUN after chane of plan figure automically

$
0
0

Dear Expert ,

 

Our organization is a nature of process industry and production plan are changing frequently , as result every time we need modify PIR and then we have perform MRP RUN through t-code MD02 . This is very tedious to end user .

 

Hence we want to develop a tool , after  changes of plan figure , at the end day , from PBIM and PBED combination,  MRP RUN will run will perform atomically.

 

Please help me how to do the configuration .

 

Regards,

Amit Biswas  

scheduling in the past

$
0
0

Dear Expert ;

 

I want to allow the scheduling in the past only in LTP.

 

I maintain scheduling type as backward 365 days ( in OPU5) on my scenario but it does not work .

so I add start in the past in "  paramter for determining the basic dates" it work in my scenario and also in the real time ?

I just want this option in LTP .

any help?


Production order without reference

$
0
0

Hi Friends,

 

Can we get a report were we can know that how many production order are created without reference to planned order.

We know how to find out through co02 but we want to check out for multiple orders.

 

Kindly help.

 

Regards,

Sun

Material forecast

$
0
0

Hi,

 

We prepare annual forecast outside the sap system. production plan and its mrp is done for make to order and make to stock materials which gives actual raw materials purchasing figure. But comparsion for raw materials requirement as per annual forecast is done outside sap. so can you suggest how can we do this from sap, so that we get requirement of raw materials against annual budget, actual requirement from mrp and balance requirement against budget forecast.

 

Regards,

sun

Tolerance for backflush (261) quantity

$
0
0

Hi there,

 

Sample BOM

 

FERT - 1000pc

.. ROH-A - 1000pc

.. ROH-B - 1000pc

 

So my BOM for FERT will consume 1000pc for every 1000pc produced

 

My question is that, if i create a Production Order for 1000pc, so during my confirmation, under the Documented Goods Movement, there will be two lines

 

ROH-A 261 1000pc

ROH-B 261 1000pc

 

Is there a place to set the tolerance? Meaning the user cannot consumer more than a certain %?

 

I know that this can be captured by Finance during month end when they see the variance. But Finance wants to prevent before it happens

T Code: CA61 & CA62

$
0
0

Hi,

 

I have a requirement that of consolidated report of CA61 & CA62. In the output of transaction CA61 & CA62, i am not able to find in which table the data is stored for few things.

 

Below is the screen shot attached:

capture.JPG

 

In this

1) Object

2) Item

3) Changed Object

4) Old Value

5) New value

 

Can anyone help me is there any functional module to get these details.

 

Thanks in advance

 

Regards,

 

V Kumar

T-code CA98

$
0
0

Hi PP experts,

 

Do you know how many materials can be inputted into CA98 in one time?

 

Regards,

Steve

BAPI For Process order confirmation COR6

$
0
0

Hi All,

 

Can you Pl let us know the BAPI for Process order confirmation which are done by COR6.

 

Requirement is,  we want to Partial confirm the Process order with Goods Movement as 261 ( Goods Issue For components)

 

Currently I am using FM-  BAPI_PROCORDCONF_CREATE_HDR.

After executing this FM , it is giving me message as Process order confirmed but actually No Goods movement is posted and PCNF status is not marked.

 

Can you Pl suggest if any step/ data is missing.

 

Thanks in advance.

 

Regards,

Sachin

Automate data creation between PLM and PP

$
0
0

Dear experts,

 

I contact you to get some advices on master data creation for PP : material, production BOM and routing.

 

Indeed, my objective is to automate data creation between a PLM tool (out of SAP) and SAP PP : basically, 90% of data
would be created in PLM tool and then transfered into SAP via interface.

 

I am looking for your advices on the best practices to implement such process :

 

What should be considered on both sides (PLM+PP) to run proper interface ?

What are your watch out in term of troubleshooting ?

Any experience or learning you can share ?

All kind of tips / advices / recommendations / warnings…

 

Thanks a lot in advance for your help !


MD4C excel report

$
0
0

hi,

we have MD4C report where we want to download the output of that report

with few fields.

Problem here is that it displays/downloads all the fields of which few

we do not need. So when we checked the layout it displays a default

layout.

 

Now is it possible that we can create a layout for the fields which we

need. Because we tried but its not giving the output as needed.

 

Please assist.

 

Thanks & Regards,

Nikhil

actual number of employees in confirmation not update the cost

$
0
0

As the requirement costing need to calculate the costing for the labors that drive the work center

They want to add the activity type price by labor

The case is the work center has 3 labors and in some time could be 2 labors

According to that I made the below formula in work center costing tab

(SAP_02 * SAP_09 * SAP_17 / SAP_08 )

1.png

And assigned it to the work center as below

 

 

2.png

 

 

Activity rate for machine 7 EGB & for labor 5 EGB

So formula calculate right as the formula test 

100 Pc per hour and operation will be 200 so need 2 hours from

 

 

3.png

 

In routing I said there are 3 employees and 100 for 1 hour for machine and labor

 

4.png

5.png

 

In production order by 500 PC found the formula calculating right

6.png

 

In confirmation I made for 300 PC with 3 labors as below

7.png

 

  • The question is why when I change the number of labors in confirmation the number of hour not updated?
  • And the actual cost calculated for the number of hours not for the number of labor
  • Should I update the number of labors and calculate the need hours out of system to update the confirmation?

Regards

Best planning strategy for my case?

$
0
0

Plant 1000 - Finished product A - this product sold only to customers

plant 2000 - Product B - this product is sold to customers and also to plant 1000

 

for product B we want to use MTO scenario (but we will plan components of product B) and for finished product A we want to use MTS scenario.

 

there will be STO's placed on plant 2000 from plant 1000 for product B. if I use MTO strategy for product B in 2000, how can I make the STO coming from plant 1000 behave like a sales order? what strategy shoudl I used for MTO product B...

Delete BOM Component with goods movements during Production confirmation CO11N

$
0
0

Hi All,

 

When i am deleting BOM line item with Goods movements screen during production order confirmation. following impacts are occuring.

 

Stock overview MMBE: - Before
Production confirmation BOM component is showing as reserved when I am deleting
BOM line item during production order confirmation & saving. Reservation
gets finished without Goods issue.

 

Missing Parts List CO24:-
Before Production confirmation BOM component is showing as missing parts in
CO24. When I am deleting BOM line item during production order confirmation
& saving. Missing Part list is not available any more in CO24.

 

COGI :- When I am deleting
BOM line item during production order confirmation & saving. In COGI component
is not available for Goods Issue anymore.

 

 

Requirement:- Deleted BOM
items should be available in COGI, MMBE as well as in CO24 whether COGI allowed or not.

Production order type determination for strategy 82

$
0
0

All,

 

We know that for strategy 82, one can have PO directly created and hence linked to the Sales Order.

Understand that checking control needs to be set up for the plant , order type combination.

 

A.] How can we influence the order type of the PO that gets created automatically? Say a ZP04 order type was created and I'd like to have this order type selected for PO creation whenever I create the SO.

B.] Also, if Sales order did have any blocks set up; will the PO get created after the blocks are released or at the instance when we save the SO?

 

Thanks.

Viewing all 1841 articles
Browse latest View live


<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>